[Ended] Adaptyst CERN sprint #6

Sprint number: 6
Dates: 13/08/2026 - 26/08/2026

Issues:

  • Make a new TUI*: done
  • Move from patched “perf” to in-house equivalent: to do
  • Add semi-automatic generation of code region names: done

*AI assistance will be tried in the context of this task. In case of problems here, the task will be postponed until after “Move from patched…” is done.

Some issues may be hidden: if you have permissions (e.g. a CERN affiliation), you can view them by logging in to the issue tracker.


Glossary of possible issue states:

  • Backlog: not scheduled in a currently-ongoing sprint.
  • To do: scheduled in a currently-ongoing sprint, but no work has begun yet.
  • In progress: the work is being carried out at the moment.
  • On hold: the work is being carried out in general, but it is not scheduled in a currently-ongoing sprint.
  • Waiting for third party: waiting for an input from another person/group at CERN.
  • Waiting for external: waiting for an input from a non-CERN person (e.g. a collaborator or an external contributor like you). We need to stress here that voluntary contributors never have any commitments towards us and are perfectly allowed to leave at any time: this is absolutely fine for us, but we’ll appreciate letting us know in this case so that we can update our planning.
  • Done: completed.